Next-Generation Telecom Infrastructure

Solution:
Data center engineering infrastructure
Industry:
Telecommunications

Background and Objectives

Growing data processing volumes and increasing loads on server equipment raised the demands on the engineering infrastructure of the telecommunications company. One of the key priorities was to upgrade cooling systems to maintain the stable temperature in server rooms.

The project covered more than 10 facilities in different regions of Ukraine, from Lviv to Odesa and from Uzhhorod to Khmelnytskyi. This geographic scope required a coordinated approach to design, equipment supply, and installation works.

At the same time, the modernization should take place without interrupting server operations. Any downtime, delays, or risks to data integrity were unacceptable. Therefore, the Compass Engineering team developed a step-by-step implementation plan that took into account the specific features of each server room and the need to ensure the uninterrupted operation of critical infrastructure.

Project Objectives

The primary objective was to increase the cooling capacity and improve the efficiency of air-conditioning systems to support the expansion of the IT infrastructure. The project included the following objectives:

Solution Implementation

Compass Engineering carried out a comprehensive range of works to modernize the engineering infrastructure at the customer’s facilities.

Cooling System Upgrade

Modern Schneider Electric chillers and air-conditioning systems were implemented to increase the cooling capacity. The equipment was selected based on the requirements of the server rooms and the potential future increase in load.

Temperature Control Automation

The upgraded infrastructure was equipped with automated environmental parameter control. This enables optimization of cooling system operation, temperature control, and improved energy efficiency.

Monitoring Integration

The cooling systems were integrated with the existing monitoring tools, ensuring remote monitoring of their status and prompt access to information about operating parameters.

Implementation Stages

The project implementation consisted of six main stages:

Special attention was paid to coordinating activities across the server rooms and adhering to the agreed schedules, resulting in the modernization without affecting server equipment operations.

Results

20% savings on cooling

The upgrade of the air-conditioning systems and implementation of automated control reduced cooling costs by 20%.

Expanding technological capabilities

The upgraded engineering infrastructure provides reserves for further expansion of server capacity without the need to upgrade the cooling system again in the coming years.

Centralized real-time monitoring

Integration with the existing monitoring systems enabled remote monitoring of environmental parameters and equipment status.

Uninterrupted operation of server rooms

The modernization was carried out without shutting down the server equipment, ensuring the sustainable operation of the critical telecommunications infrastructure.

“Modernizing the engineering infrastructure across a distributed network of server rooms is a task where not only the technical specifications of the equipment matter but also the precision of planning and coordination at every stage. We successfully upgraded the cooling systems without interrupting server operations, while improving energy efficiency and laying the foundation for the further development of the customer’s IT capacity,” Oleksandra Berezhna, the Head of the Project Management Department at Compass Engineering, said.